MK College
Bletchley Campus
Project Value: £300,000
Package: Full Electrical Package
Contractor: Borras Construction
Timeframe: 6 Weeks (July 18th 2025 – 29th August 2025)
Details
- Installation of new electrical circuits and DB's for Classrooms, Laboratories, Kitchens + Toilets
- New Fire alarm + Intruder system
- Full Installation of New 800A Switchboard for plant room
- New 400A Supplies for ASHP's
- Full installation of Plant room electrics
- Full Data installation